Description of Work

Treated effluent will be discharged into the West Credit River upstream of the watercourse crossing at Winston Churchill Boulevard, through a series of diffusers embedded into the riverbed.


Installation of the outfall will occur during the regulated period for in-water works, between June 15th and September 15th, as fish are not spawning during this time. The riverbed will be restored to its original condition following installation of the outfall.

Schedule of Work

Spring 2024 – Fall 2024

Update or Potential Impacts

Temporary lane closure(s) may be required for the installation of the outfall along Winston Churchill Boulevard. Efforts will be made to manage traffic around the work area for the safety of workers, road users and residents.

 

Work will take place from 7:00 a.m. to 5:00 p.m., Monday to Friday. Work after hours or on weekends may be required during the course of construction.

 

Increased truck traffic, dirt on roads, dust and noise may be experienced due to the construction activities. The Town, along with the Contactor, will make every effort to minimize these impacts to the community.

 

The Town will not be responsible for damage to any privately owned items on Town or County property.

 