Description of Work
Twin forcemains extending from the Sewage Pumping Station in Lions’ Club Park to the Erin Water Resource Recovery Facility (WRRF) will be installed along Water Street, Main Street (Wellington Road 124) and Wellington Road 52. Installation of the linear infrastructure was completed via open-cut trench method along Wellington Road 52 from the WRRF to the creek crossing south of Wellington Road 124. The section between the Sewage Pumping Station and the creek crossing will be installed by trenchless methods. Micro-tunneling will be the method used for the trenchless pipe installation.
Town Of Erin Team:
WSP Team:
Construction Team (Nabolsy Contracting Inc.):
Town Of Erin Team:
- Director of Infrastructure – Brian Kavanagh, P.Eng.
- Project Manager – Khalid Rahman, P.Eng.
WSP Team:
- Project Manager – Khaled El-Rahi, P.Eng.
- Project Sponsor – Michelle Albert, P.Eng., PMP
- Director, Construction – Vijay Sole, P.Eng.
- Contract Administrator – Qamar Janjua, C.E.T., RCCA
- Construction Inspector – Thomas Jayachandranmoulie
Construction Team (Nabolsy Contracting Inc.):
- Director / Project Manager – Saleh Elnabolsy
- Site Supervisor – Husam Al-Taie
- Microtunneling Subcontractor – Ward & Burke Microtunneling Ltd.